ScottishPower And Masdar Mark Engineering Milestone



ScottishPower Renewables and Abu Dhabi Future Energy Company PJSC – Masdar have completed a major construction milestone at the £4 billion East Anglia THREE offshore windfarm, with all 95 foundations now installed off the Suffolk coast.


Weighing in at 1,200-1,800 tonnes, standing 67-84 metres tall and with a diameter of up to 10.6 metres, the monopiles are the largest to be installed from a jack-up vessel in Europe.


The installation of all 95 transition pieces – 20 metres in height, 8 metres in diameter and weighing more than 400 tonnes – has also been completed.


With turbine installation already under way, offshore and onshore construction will continue at pace over the coming months, clearing the way for East Anglia THREE to become fully operational by the end of 2026, delivering 1.4GW of home-grown clean power to the UK.


Charlie Jordan, ScottishPower Renewables CEO, said:

“East Anglia THREE is our biggest windfarm ever and the completion of the foundation installation is a true engineering triumph. You only have to look at the numbers – more than 200,000 tonnes of steel anchored spot on into a seabed area the size of almost 43,000 football pitches – to get a sense of what we’ve achieved so far. It’s mind-blowing."

“And there’s more to come as the installation of the 95 turbines, with huge 115-metre blades – the biggest built and used here in the UK ­– crosses the halfway mark and we move ever closer to bringing the windfarm’s 1.4GW of clean energy to life."


“ScottishPower Renewables and Masdar are not just powering millions of homes with homegrown renewable electricity, we’re energising a cleaner, greener and more prosperous future for us all with almost £2 billion invested in the domestic supply chain, thousands of jobs supported during construction and around 100 jobs delivered during the windfarm’s lifetime. That’s not just delivering a positive impact, it’s creating a powerful legacy.”


Husain Al Meer, Executive Director, Global Offshore Wind and UK at Masdar said:

“The completion of foundation installation at East Anglia THREE is a significant milestone and a remarkable engineering achievement. It reflects the strength of our partnership with ScottishPower and the expertise of the project team and contractors, particularly Seaway7, who are working together to deliver one of the UK’s largest offshore windfarms."

“East Anglia THREE is Masdar’s first 50:50 offshore wind joint venture in the UK and forms an important part of our long-term commitment to the UK offshore wind industry. With electricity demand accelerating, offshore wind will be essential to delivering affordable, home-grown power at scale. Once operational, East Anglia THREE will provide 1.4GW of clean energy, helping to meet rising demand and strengthen the UK’s energy security.”


The foundation installation was delivered by Seaway7, with East Anglia THREE the first foundation installation campaign completed by its jack-up vessel, Seaway Ventus.


Lloyd Duthie, CEO Seaway7 said:

“We are proud to have supported ScottishPower Renewables and Masdar in reaching this important milestone for East Anglia THREE. The completion of the foundation installation campaign reflects the strength of collaboration and demonstrates what can be achieved when experienced teams work together with a shared commitment to delivering the energy transition."

"With the foundations now in place, Seaway7 continues to progress the installation of inter-array cables to bring East Anglia THREE another step closer to delivering clean, reliable power to more than one million UK homes.”


East Anglia THREE is the second project to be developed as part of Masdar and Iberdrola’s €15 billion strategic partnership and the first with ScottishPower in the UK.


The almost £2 billion invested in the UK supply chain includes foundation design by Wood Thilsted, the manufacturing of the turbine blades at Siemens Gamesa’s factory in Hull, vessel charters from Norfolk-based NR Marine Services and OEG, and support from metocean and seabed consultants Partrac.


East Anglia THREE is supporting 2,300 jobs during construction and will create around a hundred long-term roles in the East of England.


Its 1.4GW capacity will produce enough homegrown clean power for more than 1.3 million homes, providing greater energy security for the UK.

Most Read

Furniture Village Scoops Best Furniture Retailer Home Awards

Furniture Village Scoops Best Furniture Retailer Home Awards

The UK’s largest family-owned furniture retailer has scooped a major award celebrating excellence across the home and interiors industry.

Businesses Unite To Champion Greener Future At Basingstoke

Businesses Unite To Champion Greener Future At Basingstoke

Businesses, sustainability experts and young people came together in Basingstoke to explore green innovation, energy resilience and the opportunities of a more sustainable economy.

Cheshire Dairy Innovators Win Recognition For New Cow-Locating Technology

Cheshire Dairy Innovators Win Recognition For New Cow-Locating Technology

A family business from Ellesmere Port is celebrating after being highly commended in the New Product competition at the UK’s leading dairy event.

Categories

Aug 17
3 min read


ScottishPower Renewables and Abu Dhabi Future Energy Company PJSC – Masdar have completed a major construction milestone at the £4 billion East Anglia THREE offshore windfarm, with all 95 foundations now installed off the Suffolk coast.


Weighing in at 1,200-1,800 tonnes, standing 67-84 metres tall and with a diameter of up to 10.6 metres, the monopiles are the largest to be installed from a jack-up vessel in Europe.


The installation of all 95 transition pieces – 20 metres in height, 8 metres in diameter and weighing more than 400 tonnes – has also been completed.


With turbine installation already under way, offshore and onshore construction will continue at pace over the coming months, clearing the way for East Anglia THREE to become fully operational by the end of 2026, delivering 1.4GW of home-grown clean power to the UK.


Charlie Jordan, ScottishPower Renewables CEO, said:

“East Anglia THREE is our biggest windfarm ever and the completion of the foundation installation is a true engineering triumph. You only have to look at the numbers – more than 200,000 tonnes of steel anchored spot on into a seabed area the size of almost 43,000 football pitches – to get a sense of what we’ve achieved so far. It’s mind-blowing."

“And there’s more to come as the installation of the 95 turbines, with huge 115-metre blades – the biggest built and used here in the UK ­– crosses the halfway mark and we move ever closer to bringing the windfarm’s 1.4GW of clean energy to life."


“ScottishPower Renewables and Masdar are not just powering millions of homes with homegrown renewable electricity, we’re energising a cleaner, greener and more prosperous future for us all with almost £2 billion invested in the domestic supply chain, thousands of jobs supported during construction and around 100 jobs delivered during the windfarm’s lifetime. That’s not just delivering a positive impact, it’s creating a powerful legacy.”


Husain Al Meer, Executive Director, Global Offshore Wind and UK at Masdar said:

“The completion of foundation installation at East Anglia THREE is a significant milestone and a remarkable engineering achievement. It reflects the strength of our partnership with ScottishPower and the expertise of the project team and contractors, particularly Seaway7, who are working together to deliver one of the UK’s largest offshore windfarms."

“East Anglia THREE is Masdar’s first 50:50 offshore wind joint venture in the UK and forms an important part of our long-term commitment to the UK offshore wind industry. With electricity demand accelerating, offshore wind will be essential to delivering affordable, home-grown power at scale. Once operational, East Anglia THREE will provide 1.4GW of clean energy, helping to meet rising demand and strengthen the UK’s energy security.”


The foundation installation was delivered by Seaway7, with East Anglia THREE the first foundation installation campaign completed by its jack-up vessel, Seaway Ventus.


Lloyd Duthie, CEO Seaway7 said:

“We are proud to have supported ScottishPower Renewables and Masdar in reaching this important milestone for East Anglia THREE. The completion of the foundation installation campaign reflects the strength of collaboration and demonstrates what can be achieved when experienced teams work together with a shared commitment to delivering the energy transition."

"With the foundations now in place, Seaway7 continues to progress the installation of inter-array cables to bring East Anglia THREE another step closer to delivering clean, reliable power to more than one million UK homes.”


East Anglia THREE is the second project to be developed as part of Masdar and Iberdrola’s €15 billion strategic partnership and the first with ScottishPower in the UK.


The almost £2 billion invested in the UK supply chain includes foundation design by Wood Thilsted, the manufacturing of the turbine blades at Siemens Gamesa’s factory in Hull, vessel charters from Norfolk-based NR Marine Services and OEG, and support from metocean and seabed consultants Partrac.


East Anglia THREE is supporting 2,300 jobs during construction and will create around a hundred long-term roles in the East of England.


Its 1.4GW capacity will produce enough homegrown clean power for more than 1.3 million homes, providing greater energy security for the UK.

Most Read

Furniture Village Scoops Best Furniture Retailer Home Awards

Furniture Village Scoops Best Furniture Retailer Home Awards

The UK’s largest family-owned furniture retailer has scooped a major award celebrating excellence across the home and interiors industry.

Businesses Unite To Champion Greener Future At Basingstoke

Businesses Unite To Champion Greener Future At Basingstoke

Businesses, sustainability experts and young people came together in Basingstoke to explore green innovation, energy resilience and the opportunities of a more sustainable economy.

Cheshire Dairy Innovators Win Recognition For New Cow-Locating Technology

Cheshire Dairy Innovators Win Recognition For New Cow-Locating Technology

A family business from Ellesmere Port is celebrating after being highly commended in the New Product competition at the UK’s leading dairy event.

Categories

HMRC Image Rights Tax Clampdown Could Hit Sports Stars, Entertainers And Influencers

HMRC Image Rights Tax Clampdown Could Hit Sports Stars, Entertainers And Influencers

New image rights legislation due in 2028 could change how athletes, broadcasters, entertainers and influencers are taxed, with potentially significant implications for employers, talent and their advisers.

UK Active Business Numbers Back Above 2019 Level After Two-Year Fall

UK Active Business Numbers Back Above 2019 Level After Two-Year Fall

The number of active businesses in the UK has reached 2,889,575, back above its 2019 level after falling in 2023 and 2024, according to The UK Business Health Map.

Strong Occupier Demand Drives Lettings Success At Fort Kinnaird Trade Park

Strong Occupier Demand Drives Lettings Success At Fort Kinnaird Trade Park

CBRE and Ryden, acting on behalf of clients of Aberdeen Investments, have completed a series of lettings at Fort Kinnaird Trade Park, a purpose-built industrial and trade scheme.

Recent Posts

bottom of page